Infrastructure – optimization of the Chotten roundabout, Sursee
Sursee

New construction of concrete roundabout (outer diameter: 38m) incl. 3 bypasses, surface renovation KSI, adjustments to street drainage, street sewage pipe, street lighting, traffic counting loops, various service lines (third parties), bridge construction and bridge sealing,
Image gallery
Project facts
- Year
- 2015
- Location
- Sursee
- Region
- LU
Download
Services
General civil engineering and road constructionconcrete roundaboutsengineering structuresbridge constructionsealing
Key quantities
Gravel sand approx. 5400 m3; Degrees approx. 3500 m; Surface approx. 7400 tons, concrete roundabout + bus plate approx. 2780 m2, - inlet shafts approx. 65 pieces, control shafts approx. 15 pieces,
Special features
Construction under intensive inner-city traffic, inner-city, 31,000 DTV civil engineering, road construction, concrete roundabouts, bridge construction, sealing