Road construction – St. Erhard / Knutwil
St. Erhard / Knutwil

To increase traffic safety, a pedestrian protection island was created as a crossing aid on the K13 between St.Erhard and Knutwil (junction Baselstr, Hagmatt and Kantonstr.). During this work, we also carried out the following work: renewing and replacing around 320m of pipes (sewerage and electrical), road widening on the valley side including embankment, new construction of around 250m of edge edging, partial replacement of the base and binder course and complete replacement of the decking. Adding a staircase
Image gallery
Project facts
- Year
- 2025
- Location
- St. Erhard / Knutwil
- Region
- LU
Download
Services
Key quantities
120m cable protection pipe, 200m sewer DN250, 250m curbs, earth movements approx. 1450m3, case replacement approx. 500m3, amount of covering 950 tons. Line construction, civil engineering and road construction surfacing work