ARA Suhrental Figure 5

As part of an expansion and renovation, the Suhrental ARA has created a new settling and neutralization basin. As part of the ARGE TRIO Surental, we were able to devote ourselves to the construction of the plant pipeline, a stream obstruction using a natural stone wall and dewatering including surrounding work. We were also able to see the road surface with stones and surfaces.

Image gallery

Project facts

Year
2025
Location
Triengen
Region
LU
Enquire about this project

Services

Environmental workflood protectionplant pipeline constructioncivil engineering and road construction

Key quantities

Excavation 5200m3, backfilling 4050m3, service pipes up to DN800 2240 m1, terminations 250m1. Asphalt coverings 1260 tons Environmental work, flood protection, plant line construction, civil engineering and road construction