Infrastructure – Dagmersellen connection, redesign and renovation with bus stops and two concrete roundabouts
Dagmersellen

New construction of two concrete roundabouts (outer diameter: 33m and 35m) including bridge renovation, curb and pavement renovation, adjustment of the street drainage, street sewage pipe, street lighting, various. Works management (third party), new construction of two bus stops and four retaining walls made of in-situ concrete,
Image gallery
Project facts
- Year
- 2019
- Location
- Dagmersellen
- Region
- LU
Download
Services
General civil engineering and road constructionpavement renovationconcrete roundaboutsengineering structuresbridge renovation
Key quantities
Gravel sand approx. 2500 m3; Degrees approx. 5500 m; Surface approx. 7500 tons, concrete roundabout approx. 4000 m2, - inlet shafts approx. 35 pieces.
Special features
Construction under very intensive traffic volumes (DTV 17,000) civil engineering, road construction, concrete roundabouts, bridge renovation, retaining walls in concrete.