Noise barrier L-00163 and L-00164, Aarau
Aarau

Replacement noise barriers along T5 Aaretalstrasse, over a length of approx. 410 m. Dam dismantling and demolition of existing foundations. Create bored piles and base wall. Dam, shoulder and road maintenance work.
Image gallery
Project facts
- Year
- 2020
- Location
- Aarau
- Region
- AG
Download
Services
Demolition workbored pilesbase wallfoundation worksurfacing work
Key quantities
1,500 m3 of excavation and fill, 1,500 tons of excavated and inert material transported away, 435 m of cased bored piles DN 700 mm / 410 m base wall created civil engineering, road construction and noise protection